Component Shortages: Which Customer Orders Should Come First?

By Nathan Menefee

A controller circuit board is connected at a test workstation while a second board waits nearby.Component availability is determining how much some manufacturers can produce. In its October 23 earnings discussion, FANUC said its forecast reflected the components it expected to procure, and that improved procurement would allow higher production. The company described pressure across semiconductors, electrical components, cables, and mechanical parts. Its published earnings Q&A shows how a broad order book can become constrained by the materials available to fulfill it.

More recent procurement observations reinforce the scheduling problem. VersaLogic's November 4 update reported that multiple component delivery commitments had moved by more than a month. Those supplier schedule changes can force an OEM to choose which customer orders receive the parts already in stock. A defensible allocation connects each release to a build that can finish, a delivery obligation, and the consequence of making another customer wait.

Establish Which Stock Can Be Allocated

Start with the exact manufacturer part number and its approved uses. Confirm the quantity released by quality, where it sits, and whether it is already assigned to a customer, service obligation, or production order. Check ownership before moving stock between programs. Customer-owned material needs the appropriate authorization for any proposed reassignment.

Reconcile inventory held at the OEM, its assembly partners, and external warehouses. Count a transferred quantity once. Keep incoming shipments tied to their expected receiving and release dates so planners can see which builds depend on material that has yet to arrive.

Then ask production which orders can reach completion with the available parts. Include the remaining bill of materials, assembly capacity, testing, and any customer acceptance steps. A common chip issued to an assembly still waiting for a unique connector may remain tied up while another fully supplied order misses its shipment.

Compare the Consequences of Delaying Each Order

Sales should confirm the customer's actual need date and whether a partial shipment would help. Service should identify equipment already down and the quantity required to restore it. Operations should check whether a delayed job can move to another slot without disrupting subsequent commitments.

Have the responsible commercial team review delivery obligations and any agreed priorities. Record the likely consequences of delay, including a customer shutdown, an installation crew waiting, or an acceptance milestone moving. Use documented customer information and applicable agreements to support the decision.

Margin and order value can inform the comparison once those obligations are understood. Assign one accountable manager to approve the allocation, with input from procurement, production, service, and sales. Warehouse staff need a clear release instruction when several teams request the same stock.

Work Through the Competing Builds

Consider a hypothetical OEM with 600 released power-management devices. Each finished unit uses two. For simplicity, assume production losses have already been allowed for and no additional supply will become usable this week.

A service order needs 50 units to replace failed equipment, consuming 100 devices. A production customer needs 200 units by Friday, consuming 400 devices, and every other part and test resource is available. A third customer has ordered 300 units, requiring 600 devices, but a unique connector for that build is due next week.

Subject to the agreed customer priorities, allocating 100 devices to service and 400 to Friday's production order supports 250 completed units. The remaining 100 devices can be reserved for the third order while procurement pursues its 500-device shortfall. Document where that balance is held and who may authorize its release.

If the third customer can use a partial shipment, confirm that with sales and determine how many complete units the connector delivery will support. If its contractual priority requires earlier allocation, management may need to accept a delay elsewhere. The record should show both the selected plan and the customer commitments it displaces.

Make the Allocation Visible Through Fulfillment

Record each approved allocation against the customer order, build quantity, assembly site, and required release date. Update the balance when parts are issued, returned, or rejected. Ask the assembler to confirm consumption so reserved material does not remain available in another team's spreadsheet.

For inventory held externally, establish how the partner providing storage and fulfillment of customer-owned inventory receives allocation changes and prevents competing releases. Test whether a shipping request can be traced to the approval that assigned those parts.

Treat urgent exceptions as decisions that change the plan. Before approving a transfer, identify the affected build and have its owner acknowledge the revised coverage. This gives sales the information needed to update the displaced customer promptly.

Revisit the Decision When Its Assumptions Change

Set the next review around a meaningful event, such as the connector receipt, a confirmed chip shipment, or completion of the service build. Recalculate if test capacity slips or a customer changes its requested quantity.

In the example, 500 devices have a defined route into completed orders this week. The remaining balance has a named purpose and an identified shortfall. That record lets the team respond to the next delivery change with a clear view of which customer promises its inventory can support.